RECENT PROJECTS

Server Room

The server room project MES140 involved the project management of asbestos removal and subsequent reinstatement of the ceiling, lighting and fire protection in a working server room. Strict control on dust was essential due to the sensitivity of the smoke detectors in the room. The room is the hub of the IT system for the plant housing the main severs for the BMS (building management system), test data storage and plant IT system storage.
 
  The project sequence was:
  • Disable low level fire protection
  • Install a crash deck above servers
  • Install temporary fire protection below crash deck
  • Seal room above crash deck
  • Remove asbestos
  • Re-instate fire protection in place of removed asbestos
  • Construct 2 x new fire walls 2 hour rated
  • Decorate as instructed
  • Re-instate upper fire psrotection
  • Remove crash deck
  • Fit new ceiling and LED lights
  • Fit new low level fire protection
  • Repaint upper walls
 

Completed Server Room

 

 

 

 

RECENT PROJECTS

MES (NW) project management skills and technical expertise enable us to successfully undertake a wide range of contracts. With Successful Projects in Food, Aerospace, Automotive & Construction we can deliver in all manufacturing sectors.

Machine Relocation

Machine Relocation

 

Data Connection
Installation

Data Connection
Installation

 

Machine Relocations

Machine Relocations

Head Office
Hewitt House
Winstanley Road
Orrell
Wigan WN5 7XA
Telephone 01695 682 161
Mail info@mesnw.co.uk

ISOQAR niceic Chas Approved Safe Contractor Approved Northern Automotive Alliance SOCIAL
© Copyright 2021 MES (NW) Limited • Privacy Policy • Site by Heron Marketing & Joolz Design
LinkedIn Facebook LinkedIn Facebook LinkedIn Facebook LinkedIn Facebook LinkedIn Facebook LinkedIn Facebook LinkedIn Facebook LinkedIn Facebook